The Garden Island
Notice #: 0001379189-02
Notices to Motorists

Federal-Aid Project No. HSIP-300{155)
Installation of Enhanced Pavement Markers & New Milled Rumble Strip at
Various Locations-Island of Oahu – Work Order #06

Work on Coral Sea Rd. from Roosevelt Ave. to Coast Guard Station tentatively begin on Monday August 08, 2022 and is estimated to be completed by October 2022. Inclement weather may delay completion. No parking on or within 15′ of edge-line will be permitted during working hours and "No Parking" signs will be posted in all areas where anticipated work will take place.

The project includes removal of existing pavement markings/markers and installation of new pavement markings/markers & installation of centerline milled rumble strip.

The project limits will be Coral Sea Rd. from Roosevelt Ave. to Coast Guard Station
Lanes closures will be implemented during construction during the following hours:

Nightly; Sunday Night through Sunday Morning 6pm – 6am.
Work sequence will be as follows:

Location Work Period
Coral Sea Rd. from Roosevelt Ave. to Coast Guard Station
08/08/22 through
northbound/south bound 10/17/2022

Please be aware of changing conditions and adhere to posted speed limits.